The trench is 0.5 meters wide and 1 meters deep overall, with a rectangular cross-section. The previous estimate results in a total volume of 1,025 cubic meters of loose soil that needs to be removed.
It is stated that it will cost $45 per cubic meter to remove and dispose of the excavated soil. Therefore, the price of the excavation will be:
Excavation Cost = Total Volume × Cost per Cubic Meter × $45 × 1,025 m3
= $46,125
The price per unit for 200 mm diameter pipe is listed as $50 per meter length, which includes a 5% wastage. We must take the length of the pipeline into account when determining the pipe's overall cost:
The pipe's length is 2,000 meters.
The pipe's actual length will be as follows, taking 5% waste into account:
Effective Length is calculated as follows: Effective Length = Pipeline Length + (5% of Pipeline Length)
= 2,000 m + (5/100) 2,000 m
= 2,000 m + 100 m
= 2,100 meters
Now that the pipe cost has been calculated:
Pipe Cost = Effective Length Cost per meter length ($50) ×2,100
= $105,000.
The subcontract cost for supplying bedding material and backfill in the trench is listed at $35 per meter of trench length. Since the trench and pipeline lengths are equal, it is possible to determine the subcontract cost directly:
Subcontract Cost = Length of Pipeline x Trench Cost ($35/m)
= 2,000 m × $35
= $70,000
From the above calculations, the updated base cost estimate for the building of the 2-kilometer pipeline is obtained by adding the costs for excavation, pipes, and subcontracts:
Base Cost Estimate = Excavation Cost + Pipe Cost + Subcontract Cost
= $46,125 + $105,000 + 70,000
= $221,125
Consideration should be taken into account for the salary of the staff, equipment charges, waste disposal charges, indirect overhead costs, and profit margin in order to calculate the construction cost of the project and the base cost estimate for the client. The costs are broken down as follows:
Supervisor: 270 dollars per shift
$230 per shift for two machine operators.
$300 for three shifts of labor
The total daily wages for the staff, assuming two shifts, will be:
Total Personnel Wages = Supervisor's Wage + Laborers' Wage + Machine Operators' Wage Shifts
= ($270 + (2 × A$230) + (3 × A$200)) × 2 =
= (A$270 + A$460 + A$600) × 2
= A$1,330 × 2
= A$2,660
Excavator: A$900 for each shift.
A$600 per shift for gratuities
UTE: A$250 for each shift
The daily total equipment costs, assuming two shifts, will be:
Excavator, Tipper, and UTE Fees
Add Together for Total Equipment Fees
= (A$900 + A$600 + A$250) x 2
= A$1,750 × 2
= A$3,500.
The waste disposal fee is listed as A$2,500 (lump payment) for wastes such as pipe and other wastes.
$10,000 is the total cost of indirect overhead for the project.
A 5% profit margin is estimated for the construction contractor.
In order to determine the construction cost:
Construction costs are calculated as follows: Total Personnel Wages = Total Equipment Charges + Total Waste Disposal Charge + Indirect Overhead Costs
= A$ 2,660 + A$ 3,500 + A$ 2,500 + A$ 10,000
= A$ 19,660 + A$ 6,000
= A$ 25,660
To determine the cost of construction so far, it is important to multiply the building cost by the profit margin to arrive at the client's base cost estimate:
Base Cost Estimate for the Client = (Construction Cost Profit Margin)
= A$25,660 + 5% × A$25,660
= A$25,660 + A$1,283
= A$26,943
The basic cost estimate for the client is A$26,943, and the construction cost of the project is A$25,660.
Base Cost Estimate for the Client: Base Cost Estimate for the Client in A$ = Client's costs * Exchange Rate
= $5,000 * 1.35
= A$6,750
Therefore, the construction cost of the project is A$26,943, and the base cost estimate for the client is A$6,750
In Brief;
Personnel wages: Supervisor (A$270 per shift)
Machine Operators (A$230 per shift, 2 operators)
Labours (A$200 per shift, 3 labours)
Equipment charges: Excavator (A$900 per shift), Tipper (A$600 per shift), UTE (A$250 per shift)
Waste disposal charge: A$2,500
Indirect overhead costs: $10,000
Profit margin: 5%
Client's costs: $5,000
Base Cost Estimate for the Client = Construction Cost - (Profit Margin × Construction Cost)
= A$25,660 – (5% × A$25,660)
= A$25,660 - A$1,283
= A$ 24,377
Taking the percentage of the base cost estimate and add it to the project estimate to account for risks and contingencies. This can be used to determine the project estimate using the formula below by allowing 8.5% of the base estimate for risks and contingencies.
Risks and Contingencies = 8.5% of the base cost estimate
Base Cost Estimate + Risks and Contingencies = Base Cost Estimate + 8.5/100
= Project Estimate. Base Cost Estimate is Base Cost Estimate times (1 + 8.5/100).
We can now determine the project estimate using the A$6,750 base cost estimate that was previously calculated for the client:
Project Estimate = A$6,750 × (1 + 8.5% of 100)
= A$ 6,750 × (0.085)
= A$ 6,750 × 1.085
= A$ 7,332.75
Therefore, the project estimate is roughly A$ 7,332.75, taking 8.5% into account for risks and contingencies.
Cost of Excavation: $46,125 is the anticipated cost of excavating to remove the loose soil from the trench.
Pipe Costs: With a 5% wastage rate, the cost of the 200mm diameter pipe that will be installed in the project comes to $105,000.
Subcontract Cost for Bedding Material and Backfill: The trench's bedding material and backfill will cost $70,000.
Payroll: The daily salary for the project's staff, which consists of a supervisor, two machine operators, and three workers who work two shifts each day, is $2,660.
Equipment Costs: The cost to use equipment such an excavator, tipper, and UTE is $3,500 per day.
Fee for Waste Disposal: $2,500 is needed to remove and dispose of the excavated soil and other wastes.
Indirect Overhead Costs: The total indirect overhead costs for the project are $10,000.
Profit Margin: A 5% profit margin is added to the construction cost.
Recommendations and considerations for the project;
Considering the following suggestions to handle the project successfully:
You Might Also Like:-
Project Management Assignment Help
Project Management Assignment Sample Online
Ethical Leadership Experience - Management Assessment Answer
1,212,718Orders
4.9/5Rating
5,063Experts
Turnitin Report
$10.00Proofreading and Editing
$9.00Per PageConsultation with Expert
$35.00Per HourLive Session 1-on-1
$40.00Per 30 min.Quality Check
$25.00Total
FreeGet
500 Words Free
on your assignment today
Get
500 Words Free
on your assignment today
Request Callback
Doing your Assignment with our resources is simple, take Expert assistance to ensure HD Grades. Here you Go....
🚨Don't Leave Empty-Handed!🚨
Snag a Sweet 70% OFF on Your Assignments! 📚💡
Grab it while it's hot!🔥
Claim Your DiscountHurry, Offer Expires Soon 🚀🚀